Renovation maternity ward
Project description
The renovation of the maternity ward is taking place in 5 phases. In addition, the midwifery consultation is being expanded with a pleasant monitor and observation room, a multifunctional room for prenatal physiotherapy, breastfeeding classes and tours, among other things. The department will have a coffee and lounge area and a separate play corner.
- Phase 1: 5 single patient rooms (May & April 2022)
- Phase 2: 6 single and 1 double patient room (May & June 2022)
- Phase 3: logistics and nursing rooms (July & August 2022)
- Phase 4: 4 single koala rooms for neonatology (September & October 2022)
- Phase 5: midwifery consultation, waiting room & refurbishment of corridor walls (November & December 2022)
Project details
- Client: Noorderhart vzw
- Completion date: +/- december 2022
- Location: 3900 Pelt (Maesensveld 1), Belgium
- Status: partly realised
- Floor area: 1.300m²
- Type: Hospital (maternity)
- Images: Noorderhart Mariaziekenhuis + SVR-ARCHITECTS